  • 04th 十二月 2025, Lily by mosaic - Pre Start 12/05/2025

    Lily by Mosaic - Daily prestart

    - new lift weight 800kg ( please take extra care
    - mosaic site office is now level 7
    - TOILETS LOCATED ON LEVEL 1 & 32

    - TEMP SMOKO WILL BE GETTING MOVED TO B1

    NO WALKING IN UNITS WITH BOOTS ON !!!!

    NO SMOKING ON SITE

    PLEASE DO NOT CHARGE ANY LITHIUM E-BIKE OR E-SCOOTER BATTERIES ON SITE

    PLEASE MAKE SURE WE ARE BOOKING IN DELIVERYS

    Works on ground floor :
    lobby tiling

    32- BUILDERS CLEEAN - flood floor top and carpet - French wash

    - Ground floor landscaping
    - Ground Grass
    - ground floor grinding
    - GYM flooding
    - Line marking in basements


    WE ARE OPEN ON SATERDAY FOR WORKS

  • 04th 十二月 2025, Lily by mosaic - Pre Start 12/04/2025

    Lily by Mosaic - Daily prestart

    - new lift weight 800kg ( please take extra care
    - mosaic site office is now level 7
    - TOILETS LOCATED ON LEVEL 1 & 32

    - TEMP SMOKO WILL BE GETTING MOVED TO B1

    NO WALKING IN UNITS WITH BOOTS ON !!!!

    NO SMOKING ON SITE

    PLEASE DO NOT CHARGE ANY LITHIUM E-BIKE OR E-SCOOTER BATTERIES ON SITE

    PLEASE MAKE SURE WE ARE BOOKING IN DELIVERYS

    Works on ground floor :
    lobby tiling

    32- BUILDERS CLEEAN

    31-



    - Ground floor landscaping
    - Ground floor tiling
    - ground floor grinding
    - GYM flooding


    WE ARE OPEN ON SATERDAY FOR WORKS

  • 02nd 十月 2025, Lily by mosaic - Pre Start 2/10/2025

    Lily by Mosaic - Daily prestart

    Min 15 Max 30 Sunny .Chance of any rain: 10%
    Gold Coast area
    Sunny. The chance of fog in the north in the early morning. Light winds


    NO GENERAL WORKER ACCESS VIA GATE 3 / will change throughout the day

    NO SMOKING ON SITE

    PLEASE DO NOT CHARGE ANY LITHIUM E-BIKE OR E-SCOOTER BATTERIES ON SITE

    PLEASE MAKE SURE WE ARE BOOKING IN DELIVERYS

    Works on ground floor :
    . peno infills Pour
    . new site access
    . foot parth prep
    . render level 1 and ground

    32, prepaint ceilings

    31, grouting wet areas

    30, joinery delivery joinery install, pan man floor grinding

    29, mfp floor prep, joinery install

    28, timber floor laying, stone install

    27, elec fit off final paint

    26, flooring completion, elec fit off

    25 final paint

    24 defects

    Pre settlement inspection 303, 302 and 503

    Lobby carpet tiles laying on 18

    Level 1 pool tiling

    VEHICLE ACCESS GATE MOBILE PLANT IS IN OPERATION.

    ALL WORKERS ARE REMINDED TO CONSULT WITH MOSAIC SUPERVISORS / SAFETY REGARDING ANY COORDINATION OR ACCESS REQUIREMENTS.

现场天气预报
当前现场天气

最近更新: 1:21
温度: 23C (应用程序 26C)
风速: 9KMH
最大 风: 11KMH @0:21
自上午9点开始降雨: 0.0mm
最低温度: 23C @23:46 2025/12/19
最高温度: 30C @10:49 2025/12/19
阵风: 13KMH
最大风力: 15KMH @0:21


观测信息来自 - Bureau of Meteorology
观测位置 - Gold Coast Seaway、QUEENSLAND
时区 - 澳大利亚东部标准时间
预测 - 星期六、20 十二月

Sunny.
最低: 22C 最大: 32C
可能有雨。: 5%


预测信息来自 - Bureau of Meteorology
预测位置 - Gold Coast Seaway、QUEENSLAND
时区 - 澳大利亚东部标准时间
明天 - 星期日, 21 十二月

Mostly sunny.
最低: 23C 最大: 33C
可能有雨。: 20%


重要现场文件
刚到这个现场吗?

您知道这个现场的PPE要求吗?

确保您在现场的第一天有正确的安全设备。

查看现场PPE要求

到达现场后尽快开始工作。

在您方便的时候在线完成现场注册,节省您的时间。

开始注册

刚到这个现场吗?

您知道这个现场的PPE要求吗?

确保您在现场的第一天有正确的安全设备。

查看现场PPE要求

刚到这个现场吗?

到达现场后尽快开始工作。

在您方便的时候在线完成现场注册,节省您的时间。

开始注册

;