04th decembrie 2025, Lily by mosaic - Pre Start 12/05/2025
Lily by Mosaic - Daily prestart
- new lift weight 800kg ( please take extra care
- mosaic site office is now level 7
- TOILETS LOCATED ON LEVEL 1 & 32
- TEMP SMOKO WILL BE GETTING MOVED TO B1
NO WALKING IN UNITS WITH BOOTS ON !!!!
NO SMOKING ON SITE
PLEASE DO NOT CHARGE ANY LITHIUM E-BIKE OR E-SCOOTER BATTERIES ON SITE
PLEASE MAKE SURE WE ARE BOOKING IN DELIVERYS
Works on ground floor :
lobby tiling
32- BUILDERS CLEEAN - flood floor top and carpet - French wash
- Ground floor landscaping
- Ground Grass
- ground floor grinding
- GYM flooding
- Line marking in basements
WE ARE OPEN ON SATERDAY FOR WORKS -
04th decembrie 2025, Lily by mosaic - Pre Start 12/04/2025
Lily by Mosaic - Daily prestart
- new lift weight 800kg ( please take extra care
- mosaic site office is now level 7
- TOILETS LOCATED ON LEVEL 1 & 32
- TEMP SMOKO WILL BE GETTING MOVED TO B1
NO WALKING IN UNITS WITH BOOTS ON !!!!
NO SMOKING ON SITE
PLEASE DO NOT CHARGE ANY LITHIUM E-BIKE OR E-SCOOTER BATTERIES ON SITE
PLEASE MAKE SURE WE ARE BOOKING IN DELIVERYS
Works on ground floor :
lobby tiling
32- BUILDERS CLEEAN
31-
- Ground floor landscaping
- Ground floor tiling
- ground floor grinding
- GYM flooding
WE ARE OPEN ON SATERDAY FOR WORKS -
02nd octombrie 2025, Lily by mosaic - Pre Start 2/10/2025
Lily by Mosaic - Daily prestart
Min 15 Max 30 Sunny .Chance of any rain: 10%
Gold Coast area
Sunny. The chance of fog in the north in the early morning. Light winds
NO GENERAL WORKER ACCESS VIA GATE 3 / will change throughout the day
NO SMOKING ON SITE
PLEASE DO NOT CHARGE ANY LITHIUM E-BIKE OR E-SCOOTER BATTERIES ON SITE
PLEASE MAKE SURE WE ARE BOOKING IN DELIVERYS
Works on ground floor :
. peno infills Pour
. new site access
. foot parth prep
. render level 1 and ground
32, prepaint ceilings
31, grouting wet areas
30, joinery delivery joinery install, pan man floor grinding
29, mfp floor prep, joinery install
28, timber floor laying, stone install
27, elec fit off final paint
26, flooring completion, elec fit off
25 final paint
24 defects
Pre settlement inspection 303, 302 and 503
Lobby carpet tiles laying on 18
Level 1 pool tiling
VEHICLE ACCESS GATE MOBILE PLANT IS IN OPERATION.
ALL WORKERS ARE REMINDED TO CONSULT WITH MOSAIC SUPERVISORS / SAFETY REGARDING ANY COORDINATION OR ACCESS REQUIREMENTS.
Condiții meteo curente la șantier
Ultima actualizare la: 01:21
Temperatură: 23C (Aplicație 26C)
Viteza vântului: 9KMH
Max. Vânt: 11KMH @00:21
Ploaie de la 9 AM: 0,0mm
Temp min: 23C @23:46 19.12.2025
Temp max: 30C @10:49 19.12.2025
Rafală: 13KMH
Rafală max: 15KMH @00:21
Locație observație - Gold Coast Seaway, QUEENSLAND
Fus orar - Ora standard a Australiei Orientale
Prognoză - sâmbătă, 20 decembrie
Sunny.
Min: 22C Max: 32C
Șanse de ploaie: 5%
Locație prognoză - Gold Coast Seaway, QUEENSLAND
Fus orar - Ora standard a Australiei Orientale
Mâine - duminică, 21 decembrie
Mostly sunny.
Min: 23C Max: 33C
Șanse de ploaie: 20%
Cunoașteți cerințele EIP pentru acest șantier?
Asigurați-vă că aveți echipamentul de siguranță corect pentru prima zi la locație.
Începeți să lucrați mai devreme atunci când ajungeți în locație.
Finalizați înregistrarea la șantier online când doriți și economisiți timp.
Cunoașteți cerințele EIP pentru acest șantier?
Asigurați-vă că aveți echipamentul de siguranță corect pentru prima zi la locație.
Începeți să lucrați mai devreme atunci când ajungeți în locație.
Finalizați înregistrarea la șantier online când doriți și economisiți timp.