  • 04th dicembre 2025, Lily by mosaic - Pre Start 12/05/2025

    Lily by Mosaic - Daily prestart

    - new lift weight 800kg ( please take extra care
    - mosaic site office is now level 7
    - TOILETS LOCATED ON LEVEL 1 & 32

    - TEMP SMOKO WILL BE GETTING MOVED TO B1

    NO WALKING IN UNITS WITH BOOTS ON !!!!

    NO SMOKING ON SITE

    PLEASE DO NOT CHARGE ANY LITHIUM E-BIKE OR E-SCOOTER BATTERIES ON SITE

    PLEASE MAKE SURE WE ARE BOOKING IN DELIVERYS

    Works on ground floor :
    lobby tiling

    32- BUILDERS CLEEAN - flood floor top and carpet - French wash

    - Ground floor landscaping
    - Ground Grass
    - ground floor grinding
    - GYM flooding
    - Line marking in basements


    WE ARE OPEN ON SATERDAY FOR WORKS

  • 04th dicembre 2025, Lily by mosaic - Pre Start 12/04/2025

    Lily by Mosaic - Daily prestart

    - new lift weight 800kg ( please take extra care
    - mosaic site office is now level 7
    - TOILETS LOCATED ON LEVEL 1 & 32

    - TEMP SMOKO WILL BE GETTING MOVED TO B1

    NO WALKING IN UNITS WITH BOOTS ON !!!!

    NO SMOKING ON SITE

    PLEASE DO NOT CHARGE ANY LITHIUM E-BIKE OR E-SCOOTER BATTERIES ON SITE

    PLEASE MAKE SURE WE ARE BOOKING IN DELIVERYS

    Works on ground floor :
    lobby tiling

    32- BUILDERS CLEEAN

    31-



    - Ground floor landscaping
    - Ground floor tiling
    - ground floor grinding
    - GYM flooding


    WE ARE OPEN ON SATERDAY FOR WORKS

  • 02nd ottobre 2025, Lily by mosaic - Pre Start 2/10/2025

    Lily by Mosaic - Daily prestart

    Min 15 Max 30 Sunny .Chance of any rain: 10%
    Gold Coast area
    Sunny. The chance of fog in the north in the early morning. Light winds


    NO GENERAL WORKER ACCESS VIA GATE 3 / will change throughout the day

    NO SMOKING ON SITE

    PLEASE DO NOT CHARGE ANY LITHIUM E-BIKE OR E-SCOOTER BATTERIES ON SITE

    PLEASE MAKE SURE WE ARE BOOKING IN DELIVERYS

    Works on ground floor :
    . peno infills Pour
    . new site access
    . foot parth prep
    . render level 1 and ground

    32, prepaint ceilings

    31, grouting wet areas

    30, joinery delivery joinery install, pan man floor grinding

    29, mfp floor prep, joinery install

    28, timber floor laying, stone install

    27, elec fit off final paint

    26, flooring completion, elec fit off

    25 final paint

    24 defects

    Pre settlement inspection 303, 302 and 503

    Lobby carpet tiles laying on 18

    Level 1 pool tiling

    VEHICLE ACCESS GATE MOBILE PLANT IS IN OPERATION.

    ALL WORKERS ARE REMINDED TO CONSULT WITH MOSAIC SUPERVISORS / SAFETY REGARDING ANY COORDINATION OR ACCESS REQUIREMENTS.

Previsioni meteo del cantiere
Meteo attuale del cantiere

Ultimo aggiornamento su: 01:21
Temperatura: 23C (App 26C)
Velocità del vento: 9KMH
Max. Vento: 11KMH @00:21
Pioggia dalle 9.00: 0,0mm
Temp min: 23C @23:46 19/12/2025
Temp max: 30C @10:49 19/12/2025
Raffica: 13KMH
Raffiche max: 15KMH @00:21


Osservazione proveniente da - Bureau of Meteorology
Luogo di osservazione - Gold Coast Seaway, QUEENSLAND
Fuso orario - Ora standard dell’Australia orientale
Previsioni - sabato, 20 dicembre

Sunny.
Min: 22C Max: 32C
Possibilità di pioggia: 5%


Previsioni provenienti da - Bureau of Meteorology
Luogo previsioni - Gold Coast Seaway, QUEENSLAND
Fuso orario - Ora standard dell’Australia orientale
Domani - domenica, 21 dicembre

Mostly sunny.
Min: 23C Max: 33C
Possibilità di pioggia: 20%


Documenti importanti per il cantiere
Nuovo sul cantiere?

Conosci i requisiti dei DPI per questo cantiere?

Assicurati di avere l'equipaggiamento di sicurezza corretto per il primo giorno in cantiere.

Visualizza requisiti DPI del cantiere

Inizia a lavorare prima quando arrivi sul cantiere.

Completa la registrazione del cantiere online con la massima comodità e risparmia tempo.

Inizio registrazione

Nuovo sul cantiere?

Conosci i requisiti dei DPI per questo cantiere?

Assicurati di avere l'equipaggiamento di sicurezza corretto per il primo giorno in cantiere.

Visualizza requisiti DPI del cantiere

Nuovo sul cantiere?

Inizia a lavorare prima quando arrivi sul cantiere.

Completa la registrazione del cantiere online con la massima comodità e risparmia tempo.

Inizio registrazione

;