04th दिसम्बर 2025, Lily by mosaic - Pre Start 12/05/2025
Lily by Mosaic - Daily prestart
- new lift weight 800kg ( please take extra care
- mosaic site office is now level 7
- TOILETS LOCATED ON LEVEL 1 & 32
- TEMP SMOKO WILL BE GETTING MOVED TO B1
NO WALKING IN UNITS WITH BOOTS ON !!!!
NO SMOKING ON SITE
PLEASE DO NOT CHARGE ANY LITHIUM E-BIKE OR E-SCOOTER BATTERIES ON SITE
PLEASE MAKE SURE WE ARE BOOKING IN DELIVERYS
Works on ground floor :
lobby tiling
32- BUILDERS CLEEAN - flood floor top and carpet - French wash
- Ground floor landscaping
- Ground Grass
- ground floor grinding
- GYM flooding
- Line marking in basements
WE ARE OPEN ON SATERDAY FOR WORKS -
04th दिसम्बर 2025, Lily by mosaic - Pre Start 12/04/2025
Lily by Mosaic - Daily prestart
- new lift weight 800kg ( please take extra care
- mosaic site office is now level 7
- TOILETS LOCATED ON LEVEL 1 & 32
- TEMP SMOKO WILL BE GETTING MOVED TO B1
NO WALKING IN UNITS WITH BOOTS ON !!!!
NO SMOKING ON SITE
PLEASE DO NOT CHARGE ANY LITHIUM E-BIKE OR E-SCOOTER BATTERIES ON SITE
PLEASE MAKE SURE WE ARE BOOKING IN DELIVERYS
Works on ground floor :
lobby tiling
32- BUILDERS CLEEAN
31-
- Ground floor landscaping
- Ground floor tiling
- ground floor grinding
- GYM flooding
WE ARE OPEN ON SATERDAY FOR WORKS -
02nd अक्तूबर 2025, Lily by mosaic - Pre Start 2/10/2025
Lily by Mosaic - Daily prestart
Min 15 Max 30 Sunny .Chance of any rain: 10%
Gold Coast area
Sunny. The chance of fog in the north in the early morning. Light winds
NO GENERAL WORKER ACCESS VIA GATE 3 / will change throughout the day
NO SMOKING ON SITE
PLEASE DO NOT CHARGE ANY LITHIUM E-BIKE OR E-SCOOTER BATTERIES ON SITE
PLEASE MAKE SURE WE ARE BOOKING IN DELIVERYS
Works on ground floor :
. peno infills Pour
. new site access
. foot parth prep
. render level 1 and ground
32, prepaint ceilings
31, grouting wet areas
30, joinery delivery joinery install, pan man floor grinding
29, mfp floor prep, joinery install
28, timber floor laying, stone install
27, elec fit off final paint
26, flooring completion, elec fit off
25 final paint
24 defects
Pre settlement inspection 303, 302 and 503
Lobby carpet tiles laying on 18
Level 1 pool tiling
VEHICLE ACCESS GATE MOBILE PLANT IS IN OPERATION.
ALL WORKERS ARE REMINDED TO CONSULT WITH MOSAIC SUPERVISORS / SAFETY REGARDING ANY COORDINATION OR ACCESS REQUIREMENTS.
साइट का मौजूदा मौसम
अंतिम बार अपडेट किया गया: 02:21
तापमान: 23C (ऐप 26C)
हवा की गति: 7KMH
अधिकतम हवा: 11KMH @00:21
सुबह 9 बजे से बारिश: 0.0mm
न्यूनतम तापमान: 23C @23:46 19-12-2025
अधिकतम तापमान: 30C @10:49 19-12-2025
गस्ट: 9KMH
अधिकतम गस्ट: 15KMH @00:21
ऑब्जरवेशन की लोकेशन- Gold Coast Seaway, QUEENSLAND
समय क्षेत्र - ऑस्ट्रेलियाई पूर्वी मानक समय
पूर्वानुमान - शनिवार, 20 दिसम्बर
Sunny.
न्यूनतम: 22C अधिकतम: 32C
बारिश की संभावना: 5%
पूर्वानुमान वाली लोकेशन - Gold Coast Seaway, QUEENSLAND
समय क्षेत्र - ऑस्ट्रेलियाई पूर्वी मानक समय
कल - रविवार, 21 दिसम्बर
Mostly sunny.
न्यूनतम: 23C अधिकतम: 33C
बारिश की संभावना: 20%
क्या आप इस साइट के लिए आवश्यक PPE के बारे में जानते हैं?
सुनिश्चित करें कि आपके पास साइट पर पहले दिन के लिए सही सुरक्षा इक्विपमेंट हैं।
जब आप साइट पर पहुंचें, तो जल्द से जल्द काम करना शुरू कर दें।
अपनी सुविधा के अनुसार अपना साइट रजिस्ट्रेशन ऑनलाइन पूरा करें और अपना समय बचाएँ।
क्या आप इस साइट के लिए आवश्यक PPE के बारे में जानते हैं?
सुनिश्चित करें कि आपके पास साइट पर पहले दिन के लिए सही सुरक्षा इक्विपमेंट हैं।
जब आप साइट पर पहुंचें, तो जल्द से जल्द काम करना शुरू कर दें।
अपनी सुविधा के अनुसार अपना साइट रजिस्ट्रेशन ऑनलाइन पूरा करें और अपना समय बचाएँ।