Lily by Mosaic
最近のニュースレター
  • 04th 12月 2025, Lily by mosaic - Pre Start 12/05/2025

    Lily by Mosaic - Daily prestart

    - new lift weight 800kg ( please take extra care
    - mosaic site office is now level 7
    - TOILETS LOCATED ON LEVEL 1 & 32

    - TEMP SMOKO WILL BE GETTING MOVED TO B1

    NO WALKING IN UNITS WITH BOOTS ON !!!!

    NO SMOKING ON SITE

    PLEASE DO NOT CHARGE ANY LITHIUM E-BIKE OR E-SCOOTER BATTERIES ON SITE

    PLEASE MAKE SURE WE ARE BOOKING IN DELIVERYS

    Works on ground floor :
    lobby tiling

    32- BUILDERS CLEEAN - flood floor top and carpet - French wash

    - Ground floor landscaping
    - Ground Grass
    - ground floor grinding
    - GYM flooding
    - Line marking in basements


    WE ARE OPEN ON SATERDAY FOR WORKS

  • 04th 12月 2025, Lily by mosaic - Pre Start 12/04/2025

    Lily by Mosaic - Daily prestart

    - new lift weight 800kg ( please take extra care
    - mosaic site office is now level 7
    - TOILETS LOCATED ON LEVEL 1 & 32

    - TEMP SMOKO WILL BE GETTING MOVED TO B1

    NO WALKING IN UNITS WITH BOOTS ON !!!!

    NO SMOKING ON SITE

    PLEASE DO NOT CHARGE ANY LITHIUM E-BIKE OR E-SCOOTER BATTERIES ON SITE

    PLEASE MAKE SURE WE ARE BOOKING IN DELIVERYS

    Works on ground floor :
    lobby tiling

    32- BUILDERS CLEEAN

    31-



    - Ground floor landscaping
    - Ground floor tiling
    - ground floor grinding
    - GYM flooding


    WE ARE OPEN ON SATERDAY FOR WORKS

  • 02nd 10月 2025, Lily by mosaic - Pre Start 2/10/2025

    Lily by Mosaic - Daily prestart

    Min 15 Max 30 Sunny .Chance of any rain: 10%
    Gold Coast area
    Sunny. The chance of fog in the north in the early morning. Light winds


    NO GENERAL WORKER ACCESS VIA GATE 3 / will change throughout the day

    NO SMOKING ON SITE

    PLEASE DO NOT CHARGE ANY LITHIUM E-BIKE OR E-SCOOTER BATTERIES ON SITE

    PLEASE MAKE SURE WE ARE BOOKING IN DELIVERYS

    Works on ground floor :
    . peno infills Pour
    . new site access
    . foot parth prep
    . render level 1 and ground

    32, prepaint ceilings

    31, grouting wet areas

    30, joinery delivery joinery install, pan man floor grinding

    29, mfp floor prep, joinery install

    28, timber floor laying, stone install

    27, elec fit off final paint

    26, flooring completion, elec fit off

    25 final paint

    24 defects

    Pre settlement inspection 303, 302 and 503

    Lobby carpet tiles laying on 18

    Level 1 pool tiling

    VEHICLE ACCESS GATE MOBILE PLANT IS IN OPERATION.

    ALL WORKERS ARE REMINDED TO CONSULT WITH MOSAIC SUPERVISORS / SAFETY REGARDING ANY COORDINATION OR ACCESS REQUIREMENTS.

現場天気予報
現在の現場の天気

最終更新日時: 1:21
温度: 23C (アプリ 26C)
風速: 9KMH
最大風速: 11KMH @0:21
午前9時からの雨: 0.0mm
最低気温: 23C @23:46 2025/12/19
最高気温: 30C @10:49 2025/12/19
突風: 13KMH
最大突風: 15KMH @0:21


観察元 - Bureau of Meteorology
観察場所 - Gold Coast Seaway, QUEENSLAND
タイムゾーン - オーストラリア東部標準時
予測 - 土曜日, 20 12月

Sunny.
: 22C マックス: 32C
降雨の可能性: 5%パーセント


予測の出典 - Bureau of Meteorology
予測場所 - Gold Coast Seaway, QUEENSLAND
タイムゾーン - オーストラリア東部標準時
明日 - 日曜日, 21 12月

Mostly sunny.
: 23C マックス: 33C
降雨の可能性: 20%パーセント


重要な現場書類
現場に初めてですか?

この現場のPPE要件を知っていますか?

現場での初日に備えて、適切な安全装備を確保してください。

現場のPPE要件を表示

現場に到着したら、すぐに作業を開始できます。

ご都合の良い時にオンラインで現場登録を完了し、時間を節約してください。

登録を開始

現場に初めてですか?

この現場のPPE要件を知っていますか?

現場での初日に備えて、適切な安全装備を確保してください。

現場のPPE要件を表示

現場に初めてですか?

現場に到着したら、すぐに作業を開始できます。

ご都合の良い時にオンラインで現場登録を完了し、時間を節約してください。

登録を開始

;