Lily by Mosaic - Sitio de proyecto público
-
04th diciembre 2025, Lily by mosaic - Pre Start 12/05/2025
Lily by Mosaic - Daily prestart
- new lift weight 800kg ( please take extra care
- mosaic site office is now level 7
- TOILETS LOCATED ON LEVEL 1 & 32
- TEMP SMOKO WILL BE GETTING MOVED TO B1
NO WALKING IN UNITS WITH BOOTS ON !!!!
NO SMOKING ON SITE
PLEASE DO NOT CHARGE ANY LITHIUM E-BIKE OR E-SCOOTER BATTERIES ON SITE
PLEASE MAKE SURE WE ARE BOOKING IN DELIVERYS
Works on ground floor :
lobby tiling
32- BUILDERS CLEEAN - flood floor top and carpet - French wash
- Ground floor landscaping
- Ground Grass
- ground floor grinding
- GYM flooding
- Line marking in basements
WE ARE OPEN ON SATERDAY FOR WORKS -
04th diciembre 2025, Lily by mosaic - Pre Start 12/04/2025
Lily by Mosaic - Daily prestart
- new lift weight 800kg ( please take extra care
- mosaic site office is now level 7
- TOILETS LOCATED ON LEVEL 1 & 32
- TEMP SMOKO WILL BE GETTING MOVED TO B1
NO WALKING IN UNITS WITH BOOTS ON !!!!
NO SMOKING ON SITE
PLEASE DO NOT CHARGE ANY LITHIUM E-BIKE OR E-SCOOTER BATTERIES ON SITE
PLEASE MAKE SURE WE ARE BOOKING IN DELIVERYS
Works on ground floor :
lobby tiling
32- BUILDERS CLEEAN
31-
- Ground floor landscaping
- Ground floor tiling
- ground floor grinding
- GYM flooding
WE ARE OPEN ON SATERDAY FOR WORKS -
02nd octubre 2025, Lily by mosaic - Pre Start 2/10/2025
Lily by Mosaic - Daily prestart
Min 15 Max 30 Sunny .Chance of any rain: 10%
Gold Coast area
Sunny. The chance of fog in the north in the early morning. Light winds
NO GENERAL WORKER ACCESS VIA GATE 3 / will change throughout the day
NO SMOKING ON SITE
PLEASE DO NOT CHARGE ANY LITHIUM E-BIKE OR E-SCOOTER BATTERIES ON SITE
PLEASE MAKE SURE WE ARE BOOKING IN DELIVERYS
Works on ground floor :
. peno infills Pour
. new site access
. foot parth prep
. render level 1 and ground
32, prepaint ceilings
31, grouting wet areas
30, joinery delivery joinery install, pan man floor grinding
29, mfp floor prep, joinery install
28, timber floor laying, stone install
27, elec fit off final paint
26, flooring completion, elec fit off
25 final paint
24 defects
Pre settlement inspection 303, 302 and 503
Lobby carpet tiles laying on 18
Level 1 pool tiling
VEHICLE ACCESS GATE MOBILE PLANT IS IN OPERATION.
ALL WORKERS ARE REMINDED TO CONSULT WITH MOSAIC SUPERVISORS / SAFETY REGARDING ANY COORDINATION OR ACCESS REQUIREMENTS.
Tiempo en Obra actual
Última actualización el: 2:21 AM
Temperatura: 23C (Aplicación 26C)
Velocidad del viento: 7MPH
Máx. Viento: 11MPH @12:21 AM
Lluvia desde las 9 a.m.: 0.0mm
Temp mín: 23C @11:46 PM 12/19/2025
Temp máx: 30C @10:49 AM 12/19/2025
Ráfaga: 9MPH
Ráfagas máx: 15MPH @12:21 AM
Lugar de observación - Gold Coast Seaway, QUEENSLAND
Zona horaria - hora estándar de Australia oriental
Pronóstico - sábado, 20 diciembre
Sunny.
Mín: 22C Máx: 32C
Probabilidad de lluvia: 5%
Lugar de la previsión - Gold Coast Seaway, QUEENSLAND
Zona horaria - hora estándar de Australia oriental
Mañana - domingo, 21 diciembre
Mostly sunny.
Mín: 23C Máx: 33C
Probabilidad de lluvia: 20%
¿Conoce los requisitos de PPE para esta Obra?
Asegúrese de que cuento con el equipo de seguridad correcto para su primer día en la obra.
Empiece a trabajar en cuanto llegue a la obra.
Complete su registro de la obra en línea a su conveniencia y ahorre tiempo.
¿Conoce los requisitos de PPE para esta Obra?
Asegúrese de que cuento con el equipo de seguridad correcto para su primer día en la obra.
Empiece a trabajar en cuanto llegue a la obra.
Complete su registro de la obra en línea a su conveniencia y ahorre tiempo.