Lily by Mosaic - Pampublikong Lugar ng Proyekto
-
04th Disyembre 2025, Lily by mosaic - Pre Start 12/05/2025
Lily by Mosaic - Daily prestart
- new lift weight 800kg ( please take extra care
- mosaic site office is now level 7
- TOILETS LOCATED ON LEVEL 1 & 32
- TEMP SMOKO WILL BE GETTING MOVED TO B1
NO WALKING IN UNITS WITH BOOTS ON !!!!
NO SMOKING ON SITE
PLEASE DO NOT CHARGE ANY LITHIUM E-BIKE OR E-SCOOTER BATTERIES ON SITE
PLEASE MAKE SURE WE ARE BOOKING IN DELIVERYS
Works on ground floor :
lobby tiling
32- BUILDERS CLEEAN - flood floor top and carpet - French wash
- Ground floor landscaping
- Ground Grass
- ground floor grinding
- GYM flooding
- Line marking in basements
WE ARE OPEN ON SATERDAY FOR WORKS -
04th Disyembre 2025, Lily by mosaic - Pre Start 12/04/2025
Lily by Mosaic - Daily prestart
- new lift weight 800kg ( please take extra care
- mosaic site office is now level 7
- TOILETS LOCATED ON LEVEL 1 & 32
- TEMP SMOKO WILL BE GETTING MOVED TO B1
NO WALKING IN UNITS WITH BOOTS ON !!!!
NO SMOKING ON SITE
PLEASE DO NOT CHARGE ANY LITHIUM E-BIKE OR E-SCOOTER BATTERIES ON SITE
PLEASE MAKE SURE WE ARE BOOKING IN DELIVERYS
Works on ground floor :
lobby tiling
32- BUILDERS CLEEAN
31-
- Ground floor landscaping
- Ground floor tiling
- ground floor grinding
- GYM flooding
WE ARE OPEN ON SATERDAY FOR WORKS -
02nd Oktubre 2025, Lily by mosaic - Pre Start 2/10/2025
Lily by Mosaic - Daily prestart
Min 15 Max 30 Sunny .Chance of any rain: 10%
Gold Coast area
Sunny. The chance of fog in the north in the early morning. Light winds
NO GENERAL WORKER ACCESS VIA GATE 3 / will change throughout the day
NO SMOKING ON SITE
PLEASE DO NOT CHARGE ANY LITHIUM E-BIKE OR E-SCOOTER BATTERIES ON SITE
PLEASE MAKE SURE WE ARE BOOKING IN DELIVERYS
Works on ground floor :
. peno infills Pour
. new site access
. foot parth prep
. render level 1 and ground
32, prepaint ceilings
31, grouting wet areas
30, joinery delivery joinery install, pan man floor grinding
29, mfp floor prep, joinery install
28, timber floor laying, stone install
27, elec fit off final paint
26, flooring completion, elec fit off
25 final paint
24 defects
Pre settlement inspection 303, 302 and 503
Lobby carpet tiles laying on 18
Level 1 pool tiling
VEHICLE ACCESS GATE MOBILE PLANT IS IN OPERATION.
ALL WORKERS ARE REMINDED TO CONSULT WITH MOSAIC SUPERVISORS / SAFETY REGARDING ANY COORDINATION OR ACCESS REQUIREMENTS.
Kasalukuyang Panahon sa Site
Huling In-update noongPakiusap, pakibigay ang tekstong nais ipasalin. 6:21 AM
TemperaturaPakiusap, pakibigay ang tekstong nais ipasalin. 21C (App 22C)
Bilis ng HanginPakiusap, pakibigay ang tekstong nais ipasalin. 7KMH
Pinakamataas na HanginPakiusap, pakibigay ang tekstong nais ipasalin. 9KMH @2:21 AM
Umuulan mula alas-9 ng umagaPakiusap, pakibigay ang tekstong nais ipasalin. 0.0mm
Pinakamababang TemperaturaPakiusap, pakibigay ang tekstong nais ipasalin. 20C @5:51 AM
Pinakamataas na TemperaturaPakiusap, pakibigay ang tekstong nais ipasalin. 29C @10:38 AM 3/25/2026
GustPakiusap, pakibigay ang tekstong nais ipasalin. 9KMH
Max GustPakiusap, pakibigay ang tekstong nais ipasalin. 9KMH @6:21 AM
Lokasyon ng Obserbasyon - Gold Coast Seaway, QUEENSLAND
Time Zone - Standard na Oras sa Silangang Australya
Taya - Huwebes, 26 Marso
Mostly sunny.
MinPakiusap, pakibigay ang tekstong nais ipasalin. 21C MaksimumPakiusap, pakibigay ang tekstong nais ipasalin. 32C
Tiyansa ng UlanPakiusap, pakibigay ang tekstong nais ipasalin. 10%porsyento
Lokasyon ng Taya ng Panahon - Gold Coast Seaway, QUEENSLAND
Time Zone - Standard na Oras sa Silangang Australya
Bukas - Biyernes, 27 Marso
Mostly sunny.
MinPakiusap, pakibigay ang tekstong nais ipasalin. 15C MaksimumPakiusap, pakibigay ang tekstong nais ipasalin. 26C
Tiyansa ng UlanPakiusap, pakibigay ang tekstong nais ipasalin. 10%porsyento
Alam mo ba ang mga kinakailangang PPE para sa site na ito?
Tiyakin na mayroon kang tamang kagamitan sa kaligtasan para sa iyong unang araw sa site.
Magsimulang magtrabaho agad pagdating mo sa site.
Kumpletuhin ang iyong pagpaparehistro sa site online sa oras na maginhawa para sa iyo at makatipid ng oras.
Alam mo ba ang mga kinakailangang PPE para sa site na ito?
Tiyakin na mayroon kang tamang kagamitan sa kaligtasan para sa iyong unang araw sa site.
Magsimulang magtrabaho agad pagdating mo sa site.
Kumpletuhin ang iyong pagpaparehistro sa site online sa oras na maginhawa para sa iyo at makatipid ng oras.